In September, Olymel announced the completion of a C$142 million [approx. $100 million] expansion of its integrated plant in Trois-Rivières, Quebec, which quadrupled annual production capacity to 50 million kg (110 million lb). The plant now handles pork and poultry processing, slicing and packaging under one roof and produces the vast majority of Olymel’s deli meats.
Annual capacity rose from 12 to 50 million kg, and the plant was expanded from 51,700 to 137,200 sq ft (about 4,800 to 12,750 m²), nearly 2.5 times its original size. Besides La Fernandière sausages and hams, whole and sliced, it now makes most of Olymel’s deli products. The first new production lines were phased in from May 2026, after the project was announced in June 2025.
New equipment targets energy and resource use, in line with Olymel’s goal of reducing operations-related greenhouse gas emissions by 25% by 2030. An industrial battery system stores energy when demand is low and releases it when demand is high, an industry first in Canada that reduces the strain on the Hydro-Québec power grid. The plant also favors water-based over air-based cooking and uses heat recovery, closed-loop water management and reduced transportation; together, the energy efficiency initiatives are expected to cut emissions by 3,000 tonnes of CO2 equivalent per year.
The plant also uses automation and artificial intelligence. Roughly 100 jobs were created, bringing the workforce to about 400 employees. Orders worth C$110 million were placed with Canadian companies, more than C$94 million of them with local ones, and public-sector partners provided more than C$20.3 million in financial assistance, including a C$15 million loan from Investissement Québec on behalf of the provincial government.
Daniel Rivest, CEO of Olymel, on the build: “They worked tirelessly for over 15 months to bring this high-tech facility to life, and I’m very proud of that. Thanks to them, we’re now better equipped to serve our customers in Canada and around the world.”